After about one week of parallel operation, the last airlines moved from Tegel Airport to BER in the third relocation wave.
On November 4, the four-kilometer-long southern runway was officially opened with the landing of Qatar Airways flight QR81 from Doha.
On November 1, the first departures took off from BER. easyJet was the first airline to depart at Terminal 1 with a direct flight to London.
Here you can rewatch the events surrounding the opening of Terminal 1 at Berlin Brandenburg Airport Willy Brandt via the livestream video on demand.
On October 31, 2020, the new Terminal 1 of Berlin Brandenburg Airport Willy Brandt was put into operation.
On October 30, the Willy Brandt Wall was officially unveiled in honor of BER's namesake.
On October 30, the pop-up exhibition has been opened in Terminal 1 of BER.
In the night from 24th to 25th October not only summer time was changed to winter time. Also SXF is now BER T5. Insights from the first day and the opening.
On 25th october the train station was put into operation directly under Terminal 1 of BER.
On 31 October 2020, the motto was #helloBER: Berlin Brandenburg Airport started its operations. We take a look back at the commissioning.